Project Name | Pickstone Mine Project |
Client | Pickstone |
Engineers/Architect/Main Contractor | Hems Africa Engineering |
Project Type | Mine Equipping |
Period | 2023 – 2024 |
Scope | The underground scope of works entailed stripping of the old, disused structures and equipping with new equipment for the shaft and tunnels. The shaft stripping and equipping was from surface to 5.5 level, involving extensive development works being side wall supporting, shaft collar civils, shaft steel equipping, compressed air pipe fixing, shaft water pipe fixing, shaft electrical cables fixing, fabrication of kibbles, and Galloway stage. |